C05 Surface Preparation

C05.01

Why preparation decides the job

Most adhesion failures trace back to insufficient preparation. What the profile is, why laitance has to go, and the CSP number each kind of Maverick system needs before anything is installed.

  • Say what surface preparation is actually for, in one sentence
  • Explain laitance and why new concrete is never ready as-poured
  • Name the CSP range each system type requires

The whole point of preparation

Surface preparation is mechanically roughening the concrete to create a textured profile that is clean, sound, and free of bond-inhibiting contaminants. It exists for one reason: so an adequate bond exists between the concrete and the Maverick system. Many adhesion failures can be traced directly back to insufficient preparation, which makes this the step where jobs are quietly won or lost. The level of prep varies with the system being installed, and the exact method and equipment will vary job to job with conditions and access — but no matter the conditions or the equipment, the required profile has to be achieved before the floor goes down.

The ICRI concrete surface profiles
SMOOTHERROUGHERMOST MAVERICKINSTALLS LIVE HERECSP 2 to CSP 4CSP 1Acid etchedCSP 2GrindingCSP 3Light shot blastCSP 4Light scarificationCSP 5Medium shot blastCSP 6Medium scarificationCSP 7Heavy abrasive blastCSP 8ScabbledCSP 9Heavy scarificationICRI defines 10 profiles. CSP 5+ means aggressive removal, or damaged or weak concrete — a mortar is required to smooth it first.

Required profile by system type

System typeProfile required
CoatingsCSP 2 to 3
Broadcast systemsCSP 2 to 5
Self-levelersCSP 2 to 5
MortarsCSP 2 and above
Most Maverick installs overallBetween CSP 2 and CSP 4

Takeaways

  • Preparation exists to create a bond. Many adhesion failures are prep failures.
  • The higher the CSP number, the rougher the concrete. Most Maverick installs land between CSP 2 and CSP 4.
  • CSP 5 or greater means the concrete was damaged or weak — a mortar is required to smooth it before the floor goes in.