Michigan notice / lien tickler

At award, at first furnishing, at last furnishing, at any aging receivable.

  1. 01
    Open the log

    Owner of record vs. our contract party.

  2. 02
    First furnishing date

    When we first put labor or material on the job.

  3. 03
    Calendar

    Use counsel's current windows — not a blog post.

  4. 04
    Status to Eric

    Dated. No drama. A decision by [date].

  5. 05
    File proofs

    What was served, how, to whom.

Never

  • Threaten liens from your inbox.
  • Draft a claim off the internet.
  • Skip notices because the client is 'good people.'

Escalate if

  • Tickler date is inside 10 days and no decision exists.