Maverick Performance Solutions

Opening training…

0

Playbook · 20 min

Write an RFI

Two documents disagree, or the documents are silent and we would have to invent.

  1. 01
    One question

    If you have three questions, you have three RFIs.

  2. 02
    Show the conflict

    Sheet vs spec vs finish schedule, clouded.

  3. 03
    Propose a path

    Make it easy to say yes.

  4. 04
    Need-by date

    Tied to sequence, not 'ASAP.'

  5. 05
    Log + chase

    If it ages past need-by, tell Eric with the delay cost.

Never

  • Hide an RFI in a 12-topic email.
  • Ask the owner around the GC if the contract forbids it.

Escalate if

  • Silence is about to idle a crew.
  • The answer changes price or time.