Playbook · 20 min
Write an RFI
Two documents disagree, or the documents are silent and we would have to invent.
- 01One question
If you have three questions, you have three RFIs.
- 02Show the conflict
Sheet vs spec vs finish schedule, clouded.
- 03Propose a path
Make it easy to say yes.
- 04Need-by date
Tied to sequence, not 'ASAP.'
- 05Log + chase
If it ages past need-by, tell Eric with the delay cost.
Never
- Hide an RFI in a 12-topic email.
- Ask the owner around the GC if the contract forbids it.
Escalate if
- Silence is about to idle a crew.
- The answer changes price or time.
Lessons: M04.03