M02 knowledge check
How Industrial Flooring Actually Works
Pass is 80%. This is open-book — use the academy, not hope.
1. A spec calls for Section 09 67 00. That is typically:
Structural steel.
Fluid-applied / resinous flooring.
HVAC controls.
Roofing membrane.
2. Why is surface preparation the most common reason a floor fails?
Because grinders are louder than shot blasters.
Resin bonds to a prepared profile and a clean, dry, sound slab. Coat over contamination, laitance, or moisture and the system delaminates.
Because prep is not in the spec.
Because clients refuse to pay for it.
3. A pharma client says they need 'coved base.' You understand that as:
A rubber wall base glued on later.
An integral radius where floor coating turns up the wall so there is no dirt-catching joint — critical for washdown and audits.
A decorative trim color.
Only required on stairs.
4. Field reports RH in the slab above the system limit. Client wants it applied Monday. Admin should:
Tell the crew to use a thicker primer.
Hold the application, document the reading, and route a moisture-mitigation / delay decision to Eric and client in writing.
Delete the reading from the daily report so it does not scare anyone.
Ask the GC to sign a waiver on a text message.
5. On a takeoff, LF of cove and SF of floor are different because:
Cove is sold by the drum.
Floor is area (square feet); cove is a linear detail (linear feet) with different labor, material, and detail cost.
They are the same unit if you convert.
Architects only measure SF.