Fast Fill the brief
Four dates and four confirmations, on your phone, in about thirty seconds when nothing has changed from the quote.
- Open Fast Fill from the brief and sign in with the one-time code
- Enter the four dates and set Work Type, Retainage Basis and both verify fields
- Know what each field means and what a good answer looks like
Filling it
- 01Click Fast Fill (dates & work type)
The button is on the Order Brief. It opens a phone-friendly page in a new tab.
- 02Sign in
Enter your work email, then the 6-digit one-time code that arrives. The session lasts 30 days on that device.
- 03Enter the four dates
Ship Date, On-site Delivery Date, Install Start Date, Completion Date. Use the quick-pick chips rather than typing where they fit.
- 04Pick the Work Type
Subcontractor or Internal Crew. Nothing else is accepted.
- 05Pick the Retainage Basis
AIA / GC — Retainage Applies, or Direct Owner / End User — No Retainage.
- 06Set Color verified to Yes
Your confirmation that the colours on this brief are correct.
- 07Set Material/labor verified to Yes
Your confirmation that the material and the labour on this brief are correct.
What each gated field means, and a good answer
| Field | What it decides | A good answer |
|---|---|---|
| Ship Date | When material leaves the supplier. | A real date you have from the order, not a guess. |
| On-site Delivery Date | When material lands at the customer. | Far enough before install that a late truck does not idle a crew. |
| Install Start Date | When the crew mobilises. | Agreed with the customer, not aspirational. |
| Completion Date | When the work finishes. | Realistic — this prints on the Work Order and the crew works to it. |
| Work Type | Whether labour dollars appear on the Work Order at all. Subcontractor carries the price; Internal Crew never shows it. | Subcontractor or Internal Crew. The system may not guess this. |
| Retainage Basis | Whether anything is withheld from every invoice on this job. | AIA / GC — Retainage Applies for GC work; Direct Owner / End User — No Retainage for a direct owner. |
| Color verified | That the colours on the brief are right; any change from the approved quote is listed for the approver. | Yes — after you have actually looked. |
| Material/labor verified | That the material and labour on the brief are right; changes are listed for the approver. | Yes — after you have actually looked. |
Takeaways
- Fast Fill is a phone page. Sign in with your work email and a 6-digit code.
- The four dates are Ship, On-site Delivery, Install Start and Completion. Quick-pick chips save typing.
- Work Type and Retainage Basis are never guessed by the system — they change what everyone downstream sees.