M04 Project Lifecycle: Bid to Closeout

M04.02

Submittals and shop drawings

Nothing gets bought, and nothing complex gets applied, without an approved submittal.

  • Run a submittal log that a GC will respect
  • Know what 'approved as noted' actually means
  • Hold procurement until the stamp is real
Submittal cycle
  1. 01Read Div 01 + spec
  2. 02Assemble package
  3. 03Log send date
  4. 04Hold procurement
  5. 05Stamp returns
  6. 06Read every note
  7. 07Revise if required
  8. 08Release field + buying

What goes in a resinous flooring submittal

Product data (every layer), color / texture samples, moisture mitigation product if any, applicator qualifications, warranty specimen, joint and cove details, ESD test method if specified, LEED or owner-specific forms. Read Division 01 for copies, electronic vs hard, and lead times. Late submittals are how we get forced onto a specified product we cannot get.

Stamp meanings (typical — read the actual stamp)

StampAdmin action
Approved / no exceptionsProcure as submitted. File. Tell field.
Approved as notedRead every note. Revise if required. Do not bury notes.
Revise and resubmitRevise. Do not buy. Do not apply.
RejectedEric + estimating. This can be a change or a fight. Not a shrug.

Takeaways

  • The log is the job. Chasing is the work.
  • Approved as noted is not 'approved, ignore the notes.'
  • Shop drawings protect cove, pads, and drains.