Maverick Performance Solutions

Opening training…

0

M05 Field Coordination for Office Staff

M05.01

Daily reports, photos, weather, dew point

The daily report is a legal document dressed as a status update.

  • Audit a daily report for completeness
  • Treat photos as evidence with names and locations
  • Record weather and dew point without being a chemist

Why office staff touch dailies

Field writes them. You make sure they exist, they are filed, they are numbered, and they are not fiction. If a crew lead is slammed, you may type from their voice notes — but they still confirm. A daily that says 'worked on floor' cannot defend a delay claim, an extra, or a damage allegation.

Minimum daily contents

FieldExample
Job / date / authorFP-2026-HFS / 26 Aug 2026 / crew lead
CrewNames, hours, visitors, GC escort
Areas and quantitiesRoom 12: 1,400 SF grind; 40 LF cove ground
DelaysWaited 2.5 hr for lockout on Line 4. GC informed 7:10 a.m.
EnvironmentWeather, slab temp, dew point, RH if taken
MaterialsKits used, lots, shortages
Extras / RFIsFound oil at column D4 — photos, hold, PCO pending
PhotosMinimum set: start condition, prep, details, finish, issues

Takeaways

  • Thin dailies lose arguments. Thick dailies win them.
  • Photos without labels are almost useless.
  • If the crew was delayed, the reason belongs on the report the same day.

SOPSOP Section 2 — Operations & Project Management