M05 Field Coordination for Office Staff

M05.02

Scheduling, logistics, and materials

Crews, kits, and gates. The office either makes Monday possible or ruins it.

  • Build a weekly look-ahead that field will actually use
  • Match POs to application dates with lead times
  • Treat a short kit as an emergency, not a surprise

The look-aheads (7-day daily; 30-day every Monday)

  1. 01
    Where

    Job, area, system, SF/LF for the week.

  2. 02
    Who

    Crew lead, headcount, any specialty (cove, ESD testing).

  3. 03
    What must be true

    Access, demo by others, climate, COI, approved submittal, material on hand.

  4. 04
    Risks

    Moisture, other trades, owner shutdown, weather.

  5. 05
    Office tasks

    Your list: COIs, deliveries, client notices, remaining RFIs.

Logistics checklist the day before mobilize

ItemOwner
COI accepted in portal / gateAdmin
Site hours, escort, parking, dumpsterAdmin + crew lead
PPE extras, visitor needsAdmin
Equipment: blasters, grinders, vacs, spikesField
Resin, aggregate, cove strip, repair mortarAdmin receiving + field
Client notice: odor, noise, shutdownAdmin

Takeaways

  • Sequence is a promise to a plant. Protect it.
  • Material lead times are real. Custom flake blends, MMA, and ESD coatings run 4–6 weeks — not gas-station items.
  • Confirm gate, dock, hours, and escort the day before — not at 6:12 a.m.