Open a job file (award day)

The moment we have a verbal award or a PO — same day.

  1. 01
    Number

    Issue job number. Flip the Zoho Deal to Closed Won / Active Project.

  2. 02
    Create the folders

    Run /new-project — it builds the standard job subfolders (RFIs, Change-Orders, Submittals, QC-Checklists, Photos, and the rest). Copy the frozen bid set into the job file. Do not keep building in the estimate folder.

  3. 03
    Header sheet

    Client, site, vertical, contract type, values, retainage, contacts, insurance reqs.

  4. 04
    Logs

    Blank RFI, submittal, CO, COI, SDS, lien/notice logs.

  5. 05
    Ask for paper

    Contract/PO, insurance exhibit, billing instructions, portal logins.

Never

  • Spend or mobilize on a nickname and a text.
  • Leave the bid set unfrozen.

Escalate if

  • PO terms look poisonous (pay-when-paid, unlimited indemnity).
  • Insurance requirements exceed what we carry.

Lessons: M04.01M07.02